Environmental classification of facilities starts with the question that determines the cost of an environmental permit, its processing time, and the required documents: What category does your activity fall into? The difference between Category 1 and Category 3 may be the difference between an environmental management plan prepared in days and an environmental impact assessment whose review alone takes 60 business days.
Environmental Classification of Facilities: The Three Categories Defined by the Regulations
The Executive Regulations for Environmental Permits for the Establishment and Operation of Activities divide activities into three categories according to the magnitude of their environmental impact:
| Category | Official Definition (Paraphrased) | Requirements for a Construction Permit |
|---|---|---|
| Category 1 | Minor environmental impacts that do not extend beyond the activity's site boundaries | An environmental management plan (and a rehabilitation plan for specified activities) |
| Category 2 | Moderate impacts that can be mitigated and controlled and do not extend significantly beyond the site boundaries | A Category 2 environmental impact assessment |
| Category 3 | Significant environmental, social, and economic impacts that may extend beyond the site boundaries and affect sensitive areas and receptors | A scoping report, followed by a Category 3 environmental impact assessment |
Note: The categories are ordered by increasing impact, with Category 1 having the lowest impact and Category 3 the highest. Some online content reverses this order, an error that could lead you to miscalculate your project's costs.
What Determines Your Activity's Classification?
The Center classifies activities based on six factors:
- The type and scale of the activity.
- The energy used.
- The extent to which the activity depletes natural resources.
- Land uses at the site.
- Sensitive receptors surrounding the activity, such as schools, hospitals, residential complexes, and archaeological sites.
- The characteristics of the impacts themselves: their nature, extent, duration, reversibility, likelihood, and local or regional scope.
The Center issues updated guidance lists classifying different activities. These should be consulted before completing the form.
Two Similar Activities May Fall into Different Categories
Because classification depends on scale, location, and surrounding receptors—not just the type of activity—two warehouses of the same type may fall into different categories. More importantly, any activity located within an environmentally sensitive area or receptor, or within 500 meters of one, requires a detailed environmental impact assessment. The Center may also require an impact assessment for an activity outside the usual classification rules, provided that it gives reasons for its request.
How Does Classification Work in Practice?
- Complete the environmental classification form and attach the documents specified by the Center.
- Pay the form review fee (SAR 500, according to the Saudi Business Center platform).
- The Center issues its classification decision within 10 business days, or requests corrections or additional information and then makes its decision within 10 business days of receiving the requested material.
- For activities not previously classified in the Center's lists, the decision period may be extended by an additional 10 days.
Can Your Activity Be Reclassified into a Lower Category?
Yes. The regulations allow a permit applicant to request reclassification of an activity by providing evidence of modifications, measures, or improvements that reduce its environmental impact. This is where early consultation proves valuable: sometimes a change in design, waste management, or the location of a particular unit is enough to change the activity's classification and the resulting requirements and costs.
Frequently Asked Questions
Does the category determine the permit processing time? It affects it. The announced time frame for issuing approval is 10 business days for Category 1, 30 business days for Category 2, and 60 business days for Category 3.
Is choosing the category myself enough? No. The Center determines the category after reviewing the form. Your role is to provide accurate, complete information that speeds up the decision and prevents the application from being returned.
What if my activity is assigned to a higher category than I expected? You have the right to submit a written objection within 15 business days of notification, or to request reclassification after making improvements.
How Abak Green Can Help
We review your activity before you complete the form, identify the likely category and factors that could raise it, and suggest improvements that could reduce the requirements before you apply. For Category 1 activities, we prepare the required environmental management plan ourselves. For higher categories, we manage the environmental impact assessment submission through to approval. Book a preliminary review of your activity's classification.