Environmental Plans

Environmental Rehabilitation Plans and Contaminated Soil Treatment

We prepare rehabilitation plans for damaged sites and contaminated soil treatment within the environmental permit file, on closure of an activity, or when contamination is found, for industrial facilities, quarries and fuel stations, and follow implementation until the targets are met.

NCEC licensed, Category (B) Follow-up until a decision is issued
Rehabilitation Plans and Contaminated Soil Treatment

What is the rehabilitation and contaminated soil treatment service?

Environmental rehabilitation is any measure taken on an environmentally degraded or damaged site to return it to its natural state of ecological balance according to the competent authority's standards. Soil contamination is one of the most common forms of damage at industrial sites, workshops, fuel stations and warehouses.

The service covers two sides: the rehabilitation plan required in the environmental permit for some activities, and soil contamination assessment and treatment for sites that are already damaged.

A site rehabilitation plan is required in more cases than many facility owners expect: it is not only for contaminated sites, but part of the requirements of several activities from the construction stage.

When do you need this service?

  • In the construction permit for Category 1 activities: NCEC must approve the environmental rehabilitation plan for the listed activities, alongside the environmental management plan.
  • In the environmental approval for construction and operation: the plan is submitted with a declaration that the activity has no degraded or contaminated sites.
  • On closure of the activity: NCEC may include closure rules in the operation permit conditions, and site rehabilitation is a natural part of them.
  • When damage is found: the permit holder is responsible for treating any environmental impact that appears and was not stated in the submitted studies, including a fuel, oil or chemical leak.
  • After a violation: if NCEC requires you to rehabilitate the site and repair the damage.
  • Before buying or leasing an industrial site: to find out whether its soil is contaminated.

Rehabilitation is often linked to quarries and crushers, where the land's shape and cover change, so a quarry rehabilitation plan reshapes the site after extraction ends; to fuel stations and chemical warehouses because of possible soil and groundwater contamination; to old industrial sites when they close or change use; and to waste storage or disposal sites, including landfill rehabilitation after closure.

Steps of the service

  1. A site visit to identify potential contamination sources and the history of the activity.
  2. A sampling plan (locations, depths and parameters to analyse).
  3. Sampling and soil analysis through an accredited laboratory.
  4. Assessing the results against national standards.
  5. Preparing the rehabilitation and treatment plan, with timeline and cost.
  6. Submitting the plan to NCEC and supervising implementation.
  7. Final verification after treatment.

What does the service include at Abak Green?

ItemDetails
Rehabilitation plan for the permitFor the activities listed in Category 1
Soil contamination assessmentSurveying the site and identifying sources and affected areas
Soil analysisDefining the scope of analyses and carrying them out through an accredited laboratory
Treatment planChoosing the treatment method suited to the contaminant and the site
SupervisionFollowing implementation and verifying the results
Closure plansRestoring the site on closure of the activity in line with NCEC's conditions
  1. Assessing the site's current condition and the damage it has suffered.
  2. Setting the rehabilitation targets and the condition to be reached.
  3. Designing the treatment measures, including contaminated soil treatment where needed.
  4. The timeline and responsibilities.
  5. A monitoring programme proving the targets are met, and follow-up until the completion report.

Regulations governing site rehabilitation

  • The Environmental Law (M/165 dated 19/11/1441 AH).
  • Implementing Regulations for Environmental Rehabilitation: list the activities that require a rehabilitation plan.
  • Implementing Regulations for Environmental Permits: require the rehabilitation plan for the Category 1 construction permit of the listed activities, and allow NCEC to include closure conditions in the operation permit.
  • A declaration that there are no degraded or contaminated sites is one of the environmental permit requirements.
  • Breaching closure rules: from SAR 5,000 per condition for Category 1 to SAR 50,000 for Category 3.

The Implementing Regulations for Environmental Permits for Establishing and Operating Activities require NCEC's approval of the environmental rehabilitation plan for the listed activities under the Implementing Regulations for Environmental Rehabilitation, and the Saudi Business Center platform lists the plan, prepared by a licensed provider, among the requirements of the environmental approval for construction and operation. The regulations treat closure as one of the stages of the activity, so their provisions apply to it as to construction and operation. At fuel stations in particular, closure may require checking the soil condition and rehabilitating the site.

The construction permit requirements include a declaration that there are no degraded or contaminated sites, and an environmental rehabilitation plan prepared by a licensed service provider. Any environmental damage not stated in the studies, or based on incorrect information, remains the permit holder's responsibility to treat, even after the works end.

Why choose Abak Green?

  • Rehabilitation of damaged sites and contaminated soil treatment are stated explicitly in our license scope from NCEC.
  • We link results to a practical decision: what to treat, at what cost and in how long.
  • Engineering support from our parent company for site works.

The requirements state that the plan must be prepared by a service provider licensed by the National Center for Environmental Compliance, and Abak Green holds a Category (B) environmental license. We prepare the plan within the permit file, on closure, or when contamination is found, link it to the activity's environmental management plan when both are required, and follow its implementation until its targets are met.

How we work with you

  1. You send the activity's location, history and what happened there.
  2. We visit the site and send a quotation.
  3. We carry out the assessment and analyses.
  4. We hand over the report and the treatment plan.
  5. We supervise implementation until final verification.

FAQs about Rehabilitation Plans and Contaminated Soil Treatment

What is the difference between soil analysis and a site contamination assessment?

Analysis is a laboratory test of samples; an assessment is a full study that identifies the sources, extent and severity of contamination and how to treat it.

Who analyses the soil?

An accredited environmental laboratory. We define the scope of analyses, interpret the results and prepare the plan.

Is a rehabilitation plan required for every facility?

No. It is required for the activities listed in Category 1, for damaged sites, and on closure.

How long does soil treatment take?

It depends on the contaminant, the area and the treatment method, and we set it in the plan.

Do I need a soil assessment before buying an industrial site?

We recommend it, so you know the soil condition before taking responsibility for a site whose history you do not know.

Ready to start?

Send us your activity type and city, and we will define your requirements and next step.