Environmental Impact Assessment Studies

What is an environmental impact assessment?

An environmental impact assessment (EIA) is a study that identifies and evaluates the expected environmental impacts of an activity classified as Category 2 or 3, so that environmental considerations are built into the project's final design and alternatives and protection measures are defined. It is one of the most important environmental studies in the file, and the main requirement for the construction environmental permit for these two categories.

We prepare the Category 2 environmental impact assessment from data collection to NCEC's approval, and we handle the Category 3 study file.

When do you need an environmental impact assessment?

  • NCEC classified your activity as Category 2 after reviewing the classification form.
  • Your project is inside an environmentally sensitive area, or 500 metres or less from one.
  • You are making a major change to an existing activity (expansion or a change in design or operation).
  • Your construction permit expired before works started and you need an updated study.

Steps to prepare an environmental impact assessment

The stages of an environmental impact assessment for a Category 2 project are:

  1. Receiving the classification decision and defining the study scope.
  2. Collecting project data: location, processes, resources, emissions, waste and timeline.
  3. Studying the surrounding environment: physical environment, biodiversity, social aspects and sensitive receptors.
  4. Coordinating baseline measurements through an accredited laboratory when needed.
  5. Analysing and assessing the impacts on each environmental component at every project stage.
  6. Preparing mitigation, monitoring, emergency and rehabilitation plans.
  7. Submitting the study; NCEC reviews a Category 2 study within 30 working days.
  8. Answering comments until approval.

What does the environmental impact assessment include at Abak Green?

Following the structure set in the regulations for a Category 2 study:

ChapterContent
IntroductionJustification, objectives and scope of the study, and the details of the applicant and the service provider
Institutional and regulatory frameworkNational, regional and international laws, regulations and standards
Activity descriptionObjectives, location, components, resources, emissions, waste and timeline
Description of the surrounding environmentPhysical environment, biodiversity, economic and social aspects, and heritage
Impact assessmentAir, noise, odours, water, soil, health and safety, land use and waste
PlansEmergency, rehabilitation, mitigation, and environmental management and monitoring
Conclusion and annexesRoles and budget, references, maps, and material safety data sheets (MSDS)

Regulations governing environmental impact assessment

  • The Environmental Law (M/165 dated 19/11/1441 AH).
  • Implementing Regulations for Environmental Impact Assessment.
  • Implementing Regulations for Environmental Permits: Article 7 for the Category 2 study and Article 8 for the Category 3 study.
ItemCategory 2Category 3
Scoping reportNot requiredRequired, reviewed within 15 working days
Study review time30 working days60 working days
Prepared byA licensed service providerA licensed service provider
Binding resultsBinding after approvalBinding after approval

Important provisions: NCEC may reject the study if the project is split to avoid its correct classification, and failing to implement the study's commitments is a violation with a fine of SAR 20,000 per requirement for Category 2.

Why choose Abak Green?

  • Environmental impact assessments for Category 2 activities are stated in our official license scope.
  • We follow the regulations' structure chapter by chapter, so there are fewer review comments.
  • Engineering understanding of the project from our parent company makes the activity description and impact assessment more accurate.

How we work with you

  1. You send the classification decision or the project data.
  2. We define the study scope and send a quotation.
  3. We collect data and visit the site.
  4. We prepare the study and the environmental impact report and review them with you.
  5. We submit it and follow it until approval.

FAQs about Environmental Impact Assessment Studies

What is the difference between a Category 2 and a Category 3 study?

Category 3 is more comprehensive, is preceded by a scoping report, covers alternatives in more detail, and is reviewed in 60 working days compared with 30 for Category 2.

Can the project be split to lower its category?

No. NCEC may reject the study or cancel the approval if the activity is split in a way that prevents its correct classification.

Is the study binding after approval?

Yes. Its findings and recommendations become binding on the permit applicant.

In which language is the study submitted?

In Arabic; NCEC may accept some studies in English.

What if the construction permit expires before works start?

You need a new application, an updated study and a new fee.