Before you start: the construction permit
The regulation requires an environmental construction permit before any construction works begin. It is granted after the activity is classified and the environmental conditions for the construction phase are set. For Category 1 activities, the National Center for Environmental Compliance (NCEC) requires approval of an environmental management plan and a rehabilitation plan for specified activities, prepared by a licensed provider. The construction permit is valid for three years, extendable by two for large projects. Splitting a project into phases to lower its category allows NCEC to reject the study or cancel a prior approval.