An environmental permit is a document issued by the National Center for Environmental Compliance before any activity expected to affect the environment begins. Its provisions apply to every owner or operator of such an activity within the Kingdom, whether new or existing, throughout all stages: construction, operation, modification, expansion, and closure.

This guide explains environmental permit types, how facilities are classified, the requirements for each category, and officially published processing times and fees, based on the Implementing Regulations for Environmental Permits for the Construction and Operation of Activities.

An environmental permit is a document issued to a facility by the National Center for Environmental Compliance before it begins any activity with an environmental impact. There are two types: an environmental construction permit, required before construction or modification work, and an environmental operating permit, required before operating the activity. The requirements for each depend on the activity's category.

This guide explains environmental permit types, the requirements for each category, the application steps, permit validity periods, and the fines a facility may face for operating without a permit.

What Is an Environmental Permit?

The regulations define an "activity" as any industrial, commercial, or service project or facility expected to have environmental impacts. Every such activity requires a permit from the Center before it is carried out. Environmental permits are therefore not limited to large factories; workshops, warehouses, food factories, and construction sites may also be subject to these requirements, depending on the nature of their activities.

The Implementing Regulations for Environmental Permits define a permit as a document issued by the Center to a person before they begin carrying out any activity.

The regulations apply to every owner or operator of an activity with an environmental impact, whether new or existing, during construction, operation, modification, additions, expansion, and closure.

In practice, facilities that need environmental permits include factories, workshops, gas stations, hospitals and medical complexes, warehouses, construction sites, farms, and waste treatment facilities.

Type When It Is Required What It Authorizes
Environmental construction permit Before any construction work or modification to the activity Starting construction work in accordance with specified environmental conditions
Environmental operating permit Before operating the activity, and before any change to its type or size Operating and carrying out the activity
Operating permit for existing facilities For facilities previously established without a construction permit Regularizing the environmental compliance status of an existing facility

Important: A construction permit is not sufficient for operation. An operating permit must be obtained before actual activity begins.

After reviewing the environmental classification form, the Center assigns the activity to one of three categories, taking into account its type and size, energy use, resource consumption, land use, and nearby sensitive receptors.

Category Environmental Construction Permit Requirements Environmental Operating Permit Requirements
Category I (minor impact) Environmental management plan and, for specified activities, an environmental rehabilitation plan Environmental management plan
Category II (moderate impact) Category II environmental impact assessment study Environmental audit study prepared by a licensed service provider + an undertaking to implement the recommendations
Category III (major impact) Scoping report followed by a Category III environmental impact assessment study Category III environmental audit study

All these studies must be prepared by an environmental service provider licensed by the Center.

  1. Identify the application type: construction, operation, renewal, or modification.
  2. Complete the environmental classification form with details of the activity, its location, materials, and energy use.
  3. Receive the classification decision specifying the activity's category.
  4. Prepare the study required for the category through a licensed environmental service provider.
  5. Apply through the Permits and Licenses Platform and attach the study and supporting documents.
  6. Pay the applicable fees in accordance with the Implementing Regulations on Fees.
  7. The Center reviews the application and responds with approval or a request for additional information.
  8. The permit is issued with its validity period and conditions.

According to the updated implementing regulations published on the Istitlaa platform :

  • Construction permit: Valid for three years, with a possible two-year extension for major projects.
  • Operating permit: Valid for at least 3 years and no more than 6 years, depending on the activity's size and complexity.
  • Renewal for Categories II and III: Requires an environmental audit study every 3 years.
  • Classification decision: Issued within 10 business days of receiving the form.

An environmental permit is issued to a facility to construct or operate its activity. An environmental license, by contrast, is issued to those carrying out environmental activities, such as consulting companies and laboratories licensed to provide environmental services.

Obtain an environmental permit · Request a quote for your environmental permit

Is an Environmental License the Same as an Environmental Permit?

In search queries, yes: many people type "environmental license" when they mean the permit their facility needs for construction or operation, so the two terms are used interchangeably.

However, in the services provided by the National Center for Environmental Compliance, each term has a specific meaning:

  • Environmental permit: Obtained by a facility before constructing or operating its activity; this is the subject of this guide.
  • Environmental license: Issued to environmental service providers, such as organizations that prepare environmental studies and provide consulting services, as well as monitoring and testing organizations.

This is why Article (4) of the Environment Law refers to both "permit holders" and "license holders." If you have a facility you want to operate, you need a permit. Read the service details under obtaining an environmental permit for facilities.

Environmental Permit Types: Construction and Operation

  • Environmental construction permit: Required before starting any construction work or modification to the activity. It is issued after the activity is classified, its impacts are assessed, and the environmental conditions to be followed during construction are determined. It is valid for three years, and the Center may extend it by two years for large projects.
  • Environmental operating permit: Required before operating or carrying out any activity. It is issued after its requirements and those of the construction permit have been met. The Center sets its validity period at no less than three years and no more than six years, depending on the activity's size and the complexity of its operations.

On the Saudi Business Center platform, these two services are called "Environmental Approval for Construction" and "Environmental Approval for Operation."

The First Step Is Always the Environmental Classification Form

Every application begins with completing the environmental classification form and submitting it with the required documents. The Center reviews it and issues its decision on the activity category within 10 business days of receipt. It may request corrections or missing information. The period may be extended by another 10 days if the activity has not previously been classified in the Center's lists. According to the Saudi Business Center platform, the form review fee is SAR 500.

What Does Each Category Need for a Construction Permit?

Category Environmental Construction Permit Requirements
Category I The Center's approval of the environmental management plan and, for specified activities, the environmental rehabilitation plan, both prepared by a service provider licensed by the Center
Category II The Center's approval of the environmental impact assessment study for Category II activities
Category III A study scoping report, followed by the Center's approval of the environmental impact assessment study for Category III activities

Any activity located within an environmentally sensitive area or receptor, or within 500 meters of one, requires a detailed environmental impact assessment study regardless of its category.

Common Requirements According to the Saudi Business Center Platform

  • Complete the environmental classification form.
  • Submit a declaration that the activity has no degraded or contaminated sites.
  • Provide an environmental rehabilitation plan and, for operation, an environmental management plan as well, prepared by a service provider licensed by the Center.
  • Provide an industrial license for facilities located outside land designated for industrial use (for operation).
  • Provide an energy efficiency certificate for activities that require one (for operation).
  • Obtain approval from the Permanent Committee for the Protection of the Coastal Environment for projects involving land reclamation or dredging within 400 meters of the shoreline.

Processing Times and Fees

Category I Category II Category III
Approval processing time (construction or operation) 10 business days 30 business days 60 business days
Construction permit fee SAR 1,000 SAR 10,000 SAR 13,000 to SAR 275,000, depending on capital

The annual operating permit fee is calculated using the formula: environmental impact coefficient for the activity type × activity size × environmental compliance coefficient. The compliance coefficient ranges from 0.8 for highly compliant activities to 1.2 for activities with low compliance, meaning your environmental compliance directly affects the cost of your permit.

Common Mistakes That Delay Permits

  • Starting construction or operation before obtaining a permit, which is a separate violation in its own right.
  • Dividing a project and submitting it in phases in a way that prevents proper classification; in this case, the Center may reject the study or revoke a previous approval.
  • Submitting studies or plans prepared by an unlicensed organization, as the regulations require them to be submitted by a service provider licensed by the Center.
  • Allowing the construction permit to expire before work begins, which then requires a new application and a new fee.

Documents Required for an Environmental Permit

  • Commercial registration, details of the owner or authorized representative, and the national address.
  • The activity's location, coordinates, and area, along with a map showing nearby residential and commercial areas and sensitive areas.
  • A description of the activity and its purpose, and the types, quantities, and sources of raw materials.
  • Energy requirements and sources, and fuel types and quantities.
  • Estimated cost and a schedule for the activity's stages.
  • Permits and licenses already obtained by the facility.
  • The environmental study appropriate to the activity's category.

Fines for Operating Without an Environmental Permit

The regulations set fines that vary by activity category. The following are examples from the violations schedule amended in 1446 AH:

Violation Category I Category II Category III
Carrying out an activity without an environmental permit SAR 5,000 SAR 20,000 SAR 50,000
Starting construction without a valid construction permit SAR 5,000 SAR 20,000 SAR 50,000
Starting operation without a valid operating permit SAR 10,000 SAR 20,000 SAR 50,000
Modifying or adding an activity without approval SAR 5,000 SAR 20,000 SAR 50,000

Submitting incorrect information in any study or report is a serious violation, punishable by a fine of SAR 1,000 to SAR 100,000 and referral to the Public Prosecution. In all cases, the violator is required to remedy the violation and repair the damage.

Official Sources

Frequently Asked Questions

Must documents be submitted in Arabic?

Yes. The regulations require reports and studies to be submitted in Arabic, although the Center may accept some in English.

Can the Center's decision be challenged?

Yes, by submitting a written objection within 15 business days of notification. The Center decides on the objection within 30 business days.

Can an activity be reclassified into a lower category?

Yes. A permit applicant may request reclassification by providing evidence of modifications or measures that reduce the environmental impact.

Is an environmental permit mandatory for every facility?

It is required for every activity expected to have an environmental impact, whether new or existing.

Is a construction permit sufficient to operate a facility?

No. The operating permit is separate and must be obtained before the activity begins.

What study is required for a Category II operating permit?

An environmental audit study prepared by a service provider licensed by the Center, along with an undertaking to implement its findings.

I operate without a construction permit. Can I obtain an operating permit?

Yes, through the operating permit service for previously existing projects.

Do I need a new permit when expanding?

Yes. Any change to the activity's type or size requires the Center's approval and a new operating permit.

Who prepares the environmental studies for the permit?

Only an environmental service provider licensed by the Center, such as Abak Green.

How Abak Green Can Help

At Abak Green Environmental Consultancy, an office licensed by the National Center for Environmental Compliance, we complete the classification form, prepare the environmental management plan and rehabilitation plan for Category I activities, and follow up on your application until the permit is issued. For Category II and III activities, we manage the environmental impact assessment study file and work with you through to approval. Contact us for a preliminary review of your activity.