A cement plant needs an environmental permit from the National Center for Environmental Compliance before construction, followed by an operating permit before production begins. Cement manufacturing is one of the industrial activities with the most extensive environmental considerations: a quarry for raw materials, crushers and mills that generate dust, high-temperature kilns that release emissions through large stacks, and heavy transport of materials and finished products.
This guide explains the environmental permitting process for cement plants, the key environmental aspects at each production stage, required measurements, and considerations related to alternative fuels and quarries.
Steps to Obtain an Environmental Permit for a Cement Plant
- Activity classification: Submit an environmental classification form with details of production capacity, raw materials, fuel, and location. The published processing time is 10 business days, and the fee is SAR 500.
- Study based on the category assigned by the Center: An environmental impact assessment study for Category 2, or a scoping report followed by an impact assessment study for Category 3 after the Center approves the scope.
- Construction permit: The published processing time is 30 business days for Category 2, with a fee of SAR 10,000, and 60 business days for Category 3, with a fee ranging from SAR 13,000 to SAR 275,000 depending on capital.
- Operating permit before production: Requires an environmental audit study prepared by a licensed service provider for Categories 2 and 3.
- Monitoring reports after operations begin: Prepared by a licensed service provider, with monitoring and analyses performed by entities licensed in their respective fields.
The Center determines the category based on the information in the form, not the project owner. The scale of cement plants, their stacks, and their quarries makes preparing for a comprehensive impact assessment a practical consideration from the start of planning. Read the Guide to Impact Assessment Studies by Category.
Environmental Aspects at Each Production Stage
| Stage | Key Environmental Aspect | Common Control Measures |
|---|---|---|
| Quarry | Changes to the land surface, dust from blasting and excavation, and noise | A mining and rehabilitation plan, water spraying on haul routes, and scheduled blasting times |
| Crushing and grinding | Dust from transfer points and conveyors | Covered conveyors and bag filters at transfer points |
| Raw material and clinker storage | Windblown dust | Enclosed or covered storage, water spraying, and windbreaks |
| Kiln | Stack emissions of dust and gases, and carbon dioxide from fuel combustion and limestone decomposition | Emission control units, regular maintenance, and stack monitoring |
| Cement grinding and packaging | Fine dust | Dust extraction systems and filters |
| Transport | Road dust, noise, and truck emissions | Paved roads within the site, covered loads, and traffic management |
Required Measurements for Plant Stacks
The Executive Regulation for Air Quality requires annual measurements and analyses for each stack from stationary sources not subject to continuous monitoring, carried out by a licensed service provider. New facilities have a deadline for their first measurements: within 120 days of construction or 40 days of reaching target production, whichever comes first. If the plant's stacks are classified as major sources, the facility must notify the Center 30 business days before measurements and submit the results report within 40 business days of conducting them.
The limit values for each pollutant are specified in the regulation's annexes according to source type and incorporated into the plant's permit conditions. Read Air Quality and Emissions in Industrial Facilities.
Noise at the Plant Boundary
Under the Executive Regulation for Noise, the limit for industrial areas is 70 decibels during the day and 65 at night at the activity's external boundaries. Daytime runs from 7 a.m. to 8 p.m. Cement plants have numerous noise sources, including crushers, mills, large fans, and trucks. Monitoring data must be retained for three years.
Alternative Fuels Derived from Waste
In many countries, cement kilns use processed waste as an alternative fuel, such as used tires or refuse-derived fuel. In Saudi Arabia, any waste management activity requires a license or permit from the National Center for Waste Management (MWAN), and the Waste Management Law prioritizes resource recovery over disposal. Introducing waste as kiln fuel therefore involves two regulatory processes: licensing the activity through MWAN and amending the environmental permit through the National Center for Environmental Compliance, because it changes kiln operations and emissions. Read the MWAN Licensing Guide and Environmental Permit Amendments.
The Quarry and Its Rehabilitation
The quarry is part of the plant's environmental impact, even if it is located at a separate site. A rehabilitation plan should be prepared from the outset, not at closure: how areas will be worked sequentially, where topsoil will be stored, and how slopes and exhausted areas will be restored. Read Quarry Closure and Rehabilitation Plans.
A Cement Plant's Carbon Footprint
Carbon dioxide at a cement plant comes from two sources: fuel combustion in the kiln and the decomposition of limestone itself during heating. The second source is part of the chemical process, not the fuel, so it cannot be eliminated by changing fuel alone. For this reason, calculating a plant's carbon footprint distinguishes between combustion emissions and process emissions, since the methods for reducing each are different. Read the Carbon Footprint Guide.
What Does the Environmental Operating Plan Cover?
Once operations begin, inspections focus on the permit conditions and the environmental management plan. At a cement plant, these typically cover:
- Emissions: The stack measurement schedule, maintenance of emission control units, and actions to take if they fail.
- Fugitive dust: Source points, the control measure for each point, and daily inspection rounds.
- Waste: Filter dust, used oils, damaged refractories from the kiln lining, and the recipient of each waste stream.
- Water: Cooling and wash water and their discharge routes.
- Emergencies: Emission control unit failure, fuel spills, and fire. Read the Environmental Emergency Plan.
- Records: Measurement results, waste documentation, complaints from neighboring communities, and the actions taken in response.
Common Mistakes
- An impact assessment that excludes the quarry and transport: The plant, quarry, and road connecting them form a single activity in terms of their impact.
- Overlooking fugitive dust: Focusing only on the stack, even though dust from conveyors, storage areas, and roads is the leading source of complaints.
- Changing fuel without amending the permit: This is an operational change that requires approval before implementation.
- Measurements by an entity not licensed for monitoring: The results will not be accepted.
Cement Plant Checklist
- The valid permit covers the plant, quarry, and current production capacity.
- Stack measurements are scheduled with a licensed entity, with advance notification if the stacks are major sources.
- Fugitive dust sources are identified, with a documented control measure for each.
- Noise monitoring records at the plant boundary are retained for three years.
- The quarry rehabilitation plan is up to date.
- Any alternative fuel has the required MWAN license and approval for the permit amendment.
How Can Abac Green Help?
We prepare the classification form and the environmental management plan or environmental impact assessment study for Category 2, manage the Category 3 submission, prepare the audit study for the operating permit, coordinate measurements through licensed entities, and prepare monitoring reports.
Environmental Impact Assessment Study · Environmental Permits for Factories · Send your plant details for a preliminary review
Frequently Asked Questions
Does a cement plant need an environmental permit?
Yes. It needs a construction permit before building begins, followed by an operating permit before production, after the activity is classified by the National Center for Environmental Compliance.
What environmental category applies to cement plants?
The Center determines the category based on the information in the classification form. Category 2 requires an impact assessment study, while Category 3 requires a scoping report followed by an impact assessment study.
How much is the construction permit fee for a cement plant?
SAR 10,000 for Category 2 and SAR 13,000 to SAR 275,000 for Category 3, depending on capital, plus SAR 500 for review of the classification form.
How often are plant stack emissions measured?
Annually for each stack not subject to continuous monitoring, in accordance with the Executive Regulation for Air Quality, with initial measurements after construction.
What is the noise limit for a cement plant?
70 decibels during the day and 65 at night at the activity's external boundaries in industrial areas, in accordance with the Executive Regulation for Noise.
Can waste be used as fuel in a cement kiln?
This requires a license from the National Center for Waste Management for the waste management activity and approval from the National Center for Environmental Compliance to amend the permit.
Why are carbon emissions high in cement manufacturing?
Because they have two sources: fuel combustion in the kiln and limestone decomposition during heating. The second cannot be eliminated by changing fuel alone.
Is the quarry included in the plant's environmental permit?
Its impact is part of the project's environmental impact, and it requires a rehabilitation plan prepared from the outset.
Official Sources
- Category 2 Construction Permit Service: National Center for Environmental Compliance
- Category 3 Construction Permit Service: National Center for Environmental Compliance
- Executive Regulation for Air Quality (Umm Al-Qura)
- Executive Regulation for Noise (Umm Al-Qura)
- Waste Management Law: Bureau of Experts